Dubai Metro Blue Line

The Blue Line is under construction and is planned to open on 9 September 2029. It will add 30 km and 14 stations, linking Creek and Centrepoint with Dubai Festival City, Dubai Creek Harbour, International City, Dubai Silicon Oasis and Academic City.

Planned Blue Line stations

Route 1 (21 km, 10 stations)

  1. Creek
  2. Dubai Festival City
  3. Dubai Creek Harbour
  4. Ras Al Khor Industrial Area
  5. International City 1
  6. International City 2
  7. International City 3
  8. Dubai Silicon Oasis
  9. Dubai Academic City

Route 2 (9 km, 4 stations)

  1. Centrepoint
  2. Mirdif
  3. Al Warqa
  4. International City 1

Media Office list yields 13 distinct names; whether 'Emaar Properties Station' is the Dubai Creek Harbour station or a separate stop is unconfirmed. The order of the International City and Silicon Oasis stops is indicative until RTA publishes the final list.

Blue Line key facts

Opening9 September 2029 (planned)
Length30 km (15.5 km underground, 14.5 km elevated)
Stations14 (3 interchange, 7 elevated, 4 underground)
InterchangesCreek (Green Line); Centrepoint (Red Line); International City 1 (Blue Line branches)
Journey times10 to 25 minutes between key points
Expected demand320,000 passengers/day capacity by 2040
ContractAED 20.5 billion (USD 5.6 billion) contract
BuildersConsortium of MAPA (Turkey), Limak (Turkey) and CRRC (China); awarded 19 December 2024 after a tender with 5 alliances / 15 companies

Construction progress

When the Blue Line opens, the Dubai Metro network will grow to about 131 km and 78 stations. Another project, the Gold Line, has been announced for 2032: 42 km, 18 stations, about AED 34 billion, scheduled 9 September 2032.

Areas the Blue Line will serve

Frequently asked questions

When will the Dubai Metro Blue Line open?

The planned opening date is 9 September 2029, confirmed by the Dubai Media Office in May 2026.

What are the Blue Line stations?

14 stations: Creek, Dubai Festival City, Dubai Creek Harbour, Ras Al Khor Industrial Area, International City 1, International City 2, International City 3, Dubai Silicon Oasis, Dubai Academic City, Centrepoint, Mirdif, Al Warqa, plus one more station whose name is not yet confirmed (the Media Office also mentions an "Emaar Properties" station).

How much does the Blue Line cost?

AED 20.5 billion (USD 5.6 billion) contract. The contract was awarded on 19 December 2024 to a consortium of MAPA, Limak and CRRC.

How far along is construction?

About 20% complete in May 2026, when tunnelling started from International City 1; the first phase of tunnelling was completed in July 2026. The target is 30% by the end of 2026.

Where will the Blue Line connect with the other lines?

With the Green Line at Creek, with the Red Line at Centrepoint, and between its own two routes at International City 1.

Reviewed 1 October 2026.